Purpose: To help parties (Employers, Contractors, Subcontractors, Certifiers) involved in construction contracts subject to the Irish Construction Contracts Act 2013 verify compliance with key payment provisions.
Key Areas:
1. Contract Setup:
Does the contract clearly define (or provide an adequate mechanism for determining):
The amount of interim and final payments?
The 'Payment Claim Date' for each amount due?
The period between the Payment Claim Date and the Payment Due Date?
If the main contract lacks the above, are the default provisions in the CCA 2013 Schedule understood and applied?
For subcontracts, do the payment terms meet or exceed the minimum requirements set out in the CCA 2013 Schedule?
Does the contract avoid 'Pay-when-Paid' clauses (Note: Generally ineffective under CCA 2013 Section 3(5), except in specific insolvency scenarios)?
2. Executing Party (Party Claiming Payment): Payment Claim Notice (PCN) - Section 4
Was the PCN delivered to the correct party/person specified in the contract?
Was the PCN delivered no later than 5 days after the relevant Payment Claim Date?
Does the PCN clearly specify:
The amount claimed (even if zero)?
The period, stage of work, or activity the claim relates to?
The subject matter of the claim?
The basis on which the amount claimed was calculated (attach breakdown)?
3. Paying Party: Response Notice - Section 4
If contesting the amount claimed in the PCN: Was a written Response Notice delivered to the Executing Party?
Was the Response Notice delivered no later than 21 days after the relevant Payment Claim Date?
Does the Response Notice clearly specify:
The amount proposed to be paid?
The detailed reason(s) for the difference between the amount claimed and the amount proposed?
The basis on which the proposed payment amount is calculated?
If alleging breach of contract/loss/damage, specific particulars (what, when, how, value)?
If NOT contesting: Is payment of the full amount claimed in the PCN scheduled for the Payment Due Date? (Note: Failure to issue a compliant Response Notice within 21 days significantly weakens the ability to withhold payment).
4. Payment & Suspension:
Was the undisputed amount (as per PCN if no valid Response, or as per Response Notice) paid by the Payment Due Date?
If payment NOT made by Due Date (Executing Party):
Have you considered your right to suspend work under Section 5?
Has written notice been prepared specifying grounds (non-payment)?
Will notice be delivered at least 7 days before intended suspension?
Will notice be delivered no earlier than the day after the payment was due?
Has a Notice of Intention to Adjudicate been served regarding this payment (Note: Suspension may not be permissible if adjudication commenced - Section 5(3)(b))?
5. Adjudication:
Is either party aware of the right to refer any payment dispute to statutory adjudication under Section 6 at any time?
Disclaimer: This checklist is for general guidance only and is not a substitute for reading the Construction Contracts Act 2013 or obtaining professional legal/commercial advice. Compliance depends on the specific facts and contract terms.