Purpose: To help parties (Clients, Project Managers, Contractors, Supervisors) using NEC3 or NEC4 contracts follow the Early Warning (EW) process correctly to foster collaboration and mitigate risks proactively.
Key Areas:
1. Identifying Early Warnings (Clause 15/16):
(Project Manager & Contractor): Are you actively considering matters that could potentially:
Increase the total Prices?
Delay Completion or meeting a Key Date?
Impair the performance of the works in use?
(NEC4 only) Impair the performance of the Client's works (if applicable)?
Are both parties aware of their mutual obligation to raise EWs?
2. Notifying Early Warnings:
(PM & Contractor): When an EW matter is identified, is an Early Warning Notice issued as soon as reasonably possible?
Is the EW Notice communicated in writing in a form that can be read, copied, and recorded (Clause 13)?
Does the notice clearly describe the potential risk/matter?
3. Managing the Early Warning Register (Risk Register in NEC3):
Is an Early Warning Register being maintained by the Project Manager (Clause 15.2 / 16.2)?
Does the Register include:
All notified Early Warning matters?
Decisions on actions to be taken?
Who is responsible for taking those actions?
Is the Register kept up-to-date following EW meetings?
Is the Register available/issued to relevant parties?
4. Early Warning Meetings:
Does the Project Manager instruct Early Warning meetings?
Was the first EW meeting held within the contractually required timeframe (e.g., two weeks of Starting Date in NEC4)?
Are further EW meetings held regularly (as needed, or at intervals stated in Contract Data)?
Do required attendees (PM, Contractor) attend? Are others invited if needed to address specific risks?
Does the meeting focus on:
Considering proposals to avoid or reduce the impact of notified EW matters?
Seeking solutions that benefit all parties?
Deciding on actions to be taken and who will take them?
Reviewing previously agreed actions?
Are decisions and actions clearly recorded in the Early Warning Register?
5. Link to Compensation Events:
Are parties aware that failure to give an Early Warning (which could have mitigated an issue) can lead to the assessed value of a related Compensation Event being reduced (Clause 63.7 / 63.5)?
Disclaimer: This checklist is for general guidance on NEC Early Warning procedures and is not a substitute for reading the specific NEC contract clauses or obtaining professional advice. Procedures may vary based on the specific NEC version (NEC3/NEC4) and any Z clauses.